Realization of Water Management Structures
Code | Completion | Credits | Range | Language |
---|---|---|---|---|
142RVS | Z,ZK | 6 | 3P+2C | Czech |
- Relations:
- The course 142RVS can be graded only after the course 142VIZP has been successfully completed.
- Course guarantor:
- Pavel Fošumpaur
- Lecturer:
- Tomáš Dally, Pavel Fošumpaur, Karel Kříž
- Tutor:
- Tomáš Dally, Pavel Fošumpaur, Karel Kříž
- Supervisor:
- Department of Hydraulic Structures
- Synopsis:
-
The course focuses on the technological procedures in the realization of water management structures. The course is divided into two parts. The first part focuses on the implementation of sanitary engineering structures and the second part explains the procedures for the implementation of hydraulic engineering structures.
- Requirements:
-
- Active participation in seminars.
- Processing and submission of correctly and completely solved problems according to the assignment.
- Syllabus of lectures:
-
1. Organisation and introduction to the subject - basic terminology, legislative and standard documents, reading project documentation
2. Spatial arrangement of technical equipment networks, principles of routing, concurrence, crossing
3. Water supply and sewerage systems (description, design)
4. Materials of water supply and sewerage systems, basic requirements for their placement
5. Technology of construction and rehabilitation of water supply and sewerage pipelines
6. Processes and their risks in water and sewer construction (from design to operation)
7. watercourse modifications
8. Weirs
9. Waterways
10. Ponds and small reservoirs
11. Dams
12. Hydroelectric power stations
13. Operation of water management structures
- Syllabus of tutorials:
-
1. Task 1. Specification of the site of interest, requirements for submission, basics of AutoCAD, Excel, processing of documents.
2. Preparation of documents, routing of the objects in question (directional and elevation lines), assignment of the text part of the documentation.
3. Completion of routing and elevation design.
4. Detailed longitudinal profiles, water pipeline layout diagram, situational drawings.
5. Sample cross sections of pipe lay.
6. Completion of water and sewer line documentation.
7. Visit to VH laboratory - physical model.
8. Task 2. Capping of watercourse channel in the intracounty area.
9. Continuation of Task 2.
10. Completion of Task 2.
11. Task 3. Design of a small water reservoir.
12. Continuation of Task 3.
13. Completion of Task 3.
- Study Objective:
-
The aim of the study is to master technological procedures in the implementation of water management structures.
- Study materials:
-
!1. Broža, V.: Vodohospodářské stavby. Vyd. 3. Praha: ČVUT, 2005. ISBN: 80-01-03175-6.
!2. Hlavínek, P. a kol: Příručka stokování a čištění (NOEL 2002). ISBN: 80-86020-30-4.
?3. Broža, V., Čihák, F., Satrapa, L.: Hydrotechnické stavby. 1. vyd. Praha: Český svaz stavebních inženýrů, 1998. ISBN: 80-902460-5-2.
:4. ČSN 73 6005 Prostorové uspořádání sítí technického vybavení.
:5. ČSN 75 6101 Stokové sítě a kanalizační přípojky.
:6. ČSN EN 1610 Provádění stok a kanalizačních přípojek a jejich zkoušení.
:7. ČSN EN 805 Vodárenství - Požadavky na vnější sítě a jejich součásti.
:8. TNV 75 5402 Výstavba vodovodního potrubí.
- Note:
- Further information:
- Moodle předmětu
- Time-table for winter semester 2024/2025:
- Time-table is not available yet
- Time-table for summer semester 2024/2025:
-
06:00–08:0008:00–10:0010:00–12:0012:00–14:0014:00–16:0016:00–18:0018:00–20:0020:00–22:0022:00–24:00
Mon Tue Wed Thu Fri - The course is a part of the following study plans:
-
- Stavitelství (compulsory course)